Nagara Viduthi construction progress
1. 03rd Jan to 10th Jan 2023 - completed on below Works
- 3rd-floor slab shuttering and steelwork
- 2nd-floor cleaning and material shifting work
- 2nd floor Brick laying work started and is in progress.
- 1st-floor lintel shuttering and steelwork
- 3rd-floor slab concrete pouring work we will be sharing the progress updates.
2. 18th to 23rd Jan 2023 - completed on below Works
- 1st floor LINTEL above Brick work.
- 2nd floor LINTEL level brick work in progress.
- 2nd floor ceiling and column hacking work
- 4th floor column shoe concrete work
- 1st floor remaining lintel shuttering and steel work
- 1st floor lintel and sunshade concrete pouring work
- 4th floor column steel lapping work
- Bricks, river sand and 20mm Aggregate has been arrived for construction work.
- Lintel sunshade Water poured
3. 28th March to 5th April 2023 - completed on below Works
- OHT and LIFT column shuttering and steel work
- Parapet Brick laying work
- 4th floor shuttering and steel work
- 4th floor lintel concrete pouring work
- 4th floor lintel above brick laying work
- 3rd floor plastering work
- 4th floor column steel lapping work
- Cements, Bricks and river sand (Plastering) has arrived for construction work.
4. 4th to 10th May 2023 - completed on below Works
- Sunken area plastering work
- Lift side wall brick laying work
- OHT top cover slab and terrace bathroom shuttering and steel work
- sand cleaning and materials shifting work
- OHT slab ,terrace, lift beam concrete pouring work
- Water poured
- Scaffolding work
5. 18th to 23rd May - completed on below Works
- Outer scaffolding (west)
- Outer plastering work (East)side completed
- 4th-floor plastering work
- Ground floor modification work
- River sand cleaning and materials shifting work
- 2nd-floor 1st coat putty applied.
- 1st and 2nd-floor Plumbing line work.
6. 24th to 31st May - completed on below Works
- 4th floor plastering work
- Outer scaffolding and plastering work (west side)
- 1st ,2nd ,3rd floor plumbing floor line work
- 2nd floor 1st ,2nd coat putty applying work and rubbing work
- 3rd floor 1st coat putty applying work
7. 8th to 14th June - completed on below Works
- Staircase Area chipping and plastering work
- North side Outer plastering work completed
- 4th-floor door frame fixing work
- 3rd-floor 2nd coat putty and rubbing work
- OHT plastering and chipping work
- Staircase entrance shuttering and lintel concrete pouring work
- Sand cleaning and materials shifting work
8. 15th to 21st June - completed on below Works
- Staircase chipping and plastering work
- Headroom and lift room outer plastering work
- Lift entrance lintel above brickwork
- Sand cleaning and materials shifting work
- Parapet plastering work
- Lift inner button mark fixing work
- 4th-floor 1st coat putty applying for work
- Cement has arrived for construction work.